The regulation of data centers has opened a new front between the Government and the technology industry. The National Commission of Markets and Competition (CNMC) has noted that promoters have begun to renounce access permits to the electrical grid for 1,600 megawatts (MW), a capacity equivalent to the connection of 16 large data centers of 100 MW each. The figure also represents 40% of the electrical demand that the Executive itself forecasts for the sector in 2030.
The data provides a first measure of the consequences of the new regulatory requirements, but it does not allow concluding that 16 facilities have been canceled nor that investments have been moved to other countries. The supervisor's report does not identify the affected companies nor determine how many projects are behind the renunciations. The CNMC also warns that when it prepared its analysis, it still did not have all the information about the most recent withdrawals.
The CNMC has noted that promoters have begun to renounce access permits to the electrical grid for 1,600 megawatts (MW), a capacity equivalent to the connection of 16 large data centers
The unknown is relevant because Spain aspires to capture a part of the investments that accompany the development of artificial intelligence and digital services. Data centers are essential infrastructures for storing and processing information, but they require large amounts of electricity, guaranteed connections to the grid, and cooling systems. Energy availability has thus become one of the factors that determine where these infrastructures are installed and which projects can move forward.
The sector has been alerting that the design of the new regulation may reduce Spain's attractiveness compared to other European markets. SpainDC, the association that groups data center companies, has demanded urgent changes and argues that the accumulation of obligations, adaptation deadlines, and the penalties foreseen may compromise already initiated projects and hinder new investments. The organization estimates that, in a continuity scenario, the sector could mobilize 66.9 billion euros of direct and indirect investment between 2026 and 2030. It has also warned that the current text could jeopardize a substantial part of that volume, although this is a sectoral estimate, not of investments whose cancellation is accredited.
A market of permits far above the expected demand
The magnitude of the applications helps to understand why the Government has decided to intervene. According to the data collected in the CNMC report, Spain has granted around 12,000 MW of electrical permits for data centers, while another 27,000 MW are still in processing and more than 32,000 MW have been denied. The sum of granted and requested capacity far exceeds the needs that the Executive estimates for the end of the decade.
The 2024 Artificial Intelligence Strategy contemplates reaching 2,500 MW of computing power by 2030, equivalent to an electrical demand of between 3,500 and 4,000 MW. That is to say, the permits already granted for data centers approximately triple the expected electrical demand for the sector. The comparison does not mean that all that power will be consumed nor that each permit corresponds to an installation that will be built: precisely, part of the applications may not materialize.
The Executive wants to prevent promoters from reserving electrical capacity for projects that are not progressing, preventing other consumers from accessing it. The problem affects both the planning of networks and the competition for a limited resource. If infrastructures are sized to meet a demand that ultimately does not appear, unnecessary investments may be made; if all applications are granted, the pressure on the system could hinder the connection of other industries.
The CNMC shares that concern. Its warning, therefore, does not equate to a rejection of regulation, but rather a call to find a balance between market organization, project viability, and competition.
80% of electricity, backed by new renewable generation
The draft royal decree promoted by the Ministry for the Ecological Transition introduces specific requirements for energy and environmental sustainability, in addition to conditions for resilience and digital sovereignty. One of the most controversial obligations is that data centers must back at least 80% of their electrical consumption with new renewable generation, with hour-by-hour accreditation. The proposal also includes requirements for energy and water efficiency and conditions regarding who operates the facilities and where the data related to their operation is maintained.
The logic of the Government is that the growth of infrastructure that consumes electricity intensively should not compromise energy and environmental objectives. The Executive wants the digital deployment to be accompanied by new renewable capacity, to reduce the impact of installations, and for the data to be subject to European legal guarantees.
For operators, however, the combined effect of the requirements can raise costs and complicate planning. Data centers are designed with long investment horizons: before becoming operational, their promoters may have committed land, financing, equipment, construction, and energy agreements. Modifying the conditions during the development of a project can force a review of its economic calculations and timelines.
SpainDC argues that the proposed demands may place Spain in a less competitive position than that of other European countries. This warning expresses the position of the employers' association and should be contrasted with the actual conditions of alternative markets and with the impact that the approved text ultimately has.
The CNMC calls for moderating the toughest requirements
The debate has taken on a new dimension with the report that the CNMC approved on September 22. The agency recommends reviewing several elements of the project and warns that some obligations could distort the market, generate excessive costs, and hinder the viability of certain investments.
Among the questioned aspects are the rigidity of the renewable coverage obligation, its hourly correlation, compliance deadlines, and certain criteria for energy and water efficiency. The CNMC also proposes reviewing the surcharges planned for cases of non-compliance. Its recommendations are not binding: it is up to the Government to decide what changes to incorporate before approving the regulation.
The regulator thus puts a central issue on the table for the design of the regulation: how to prevent environmental and energy obligations from becoming disproportionate barriers to the entry of new operators. The requirement for new renewable generation can drive clean investments, but its application must take into account development timelines, the availability of projects, and the capacity of promoters to contract or build that generation.
The dispute is not limited, therefore, to choosing between sustainability and investment. It also affects how the costs of the energy transition are distributed, what conditions digital infrastructures must meet, and to what extent regulation can adapt to a rapidly expanding sector.
The pending question: which projects are abandoning Spain
The figure of 1,600 MW confirms that there are renunciations of electrical permits, but it does not allow knowing their final economic impact. It is not known how many installations are behind the withdrawals, what degree of development they had reached, or whether their promoters have decided to abandon Spain, postpone their plans, or renounce capacity reservations that they did not need.
This distinction is fundamental. If the renunciations correspond to speculative projects that were never going to be built, regulation could free up resources for investments with greater execution guarantees. If, on the contrary, they affect advanced initiatives that desist due to the tightening of conditions, Spain could lose opportunities in the international race to attract artificial intelligence infrastructures.
The next update of the CNMC data, the Ministry's response to the regulator's recommendations, and the changes incorporated into the royal decree will allow for better measurement of the consequences. It will also be necessary to contrast the warnings of the employers' association with concrete information from the affected promoters and with data on investment that has actually been canceled or relocated.
For now, the evidence outlines a conflict between two legitimate objectives: preventing electrical permits from being blocked by projects that are not executed and maintaining a sufficiently competitive framework to attract technological investments. The unknown is no longer just how much capacity is being freed up, but whether the Government will manage to organize the market without jeopardizing viable projects. That will be the decisive measure of success —or of the limits— of the new regulation.