Investor flight in data centers: what is happening?

The CNMC notes renunciations of electrical permits for 1,600 MW while calling for the easing of some of the requirements of the decree that the Government is preparing. SpainDC warns that the regulation could compromise million-dollar investments.

transición digital emisiones

transición digital emisiones

Add DEMÓCRATA to Google

Ask FREN

Published

Last updated

6 minutes

Most read

Elecciones 29N · Encuestas

La media de las encuestas

Media a 16 de noviembre de 2026 · 17 institutos

  • PP31,5 %
  • PSOE27,2 %
  • Vox18,9 %
  • Frente Amplio6,4 %
  • ERC2,5 %
01020304050ene 2024jul 2024ene 2025jul 2025ene 2026jul 2026

Media del último estudio de cada instituto en 30 días y su evolución semanal desde el 23J. Partidos con al menos un 2 %.

Todas las encuestas

Elecciones generales del 29 de noviembre · Demócrata

The regulation of data centers has opened a new front between the Government and the technology industry. The National Commission of Markets and Competition (CNMC) has noted that promoters have begun to renounce access permits to the electrical grid for 1,600 megawatts (MW), a capacity equivalent to the connection of 16 large data centers of 100 MW each. The figure also represents 40% of the electrical demand that the Executive itself forecasts for the sector in 2030.

The data provides a first measure of the consequences of the new regulatory requirements, but it does not allow concluding that 16 facilities have been canceled nor that investments have been moved to other countries. The supervisor's report does not identify the affected companies nor determine how many projects are behind the renunciations. The CNMC also warns that when it prepared its analysis, it still did not have all the information about the most recent withdrawals.

The CNMC has noted that promoters have begun to renounce access permits to the electrical grid for 1,600 megawatts (MW), a capacity equivalent to the connection of 16 large data centers

The unknown is relevant because Spain aspires to capture a part of the investments that accompany the development of artificial intelligence and digital services. Data centers are essential infrastructures for storing and processing information, but they require large amounts of electricity, guaranteed connections to the grid, and cooling systems. Energy availability has thus become one of the factors that determine where these infrastructures are installed and which projects can move forward.

The sector has been alerting that the design of the new regulation may reduce Spain's attractiveness compared to other European markets. SpainDC, the association that groups data center companies, has demanded urgent changes and argues that the accumulation of obligations, adaptation deadlines, and the penalties foreseen may compromise already initiated projects and hinder new investments. The organization estimates that, in a continuity scenario, the sector could mobilize 66.9 billion euros of direct and indirect investment between 2026 and 2030. It has also warned that the current text could jeopardize a substantial part of that volume, although this is a sectoral estimate, not of investments whose cancellation is accredited.

A market of permits far above the expected demand

The magnitude of the applications helps to understand why the Government has decided to intervene. According to the data collected in the CNMC report, Spain has granted around 12,000 MW of electrical permits for data centers, while another 27,000 MW are still in processing and more than 32,000 MW have been denied. The sum of granted and requested capacity far exceeds the needs that the Executive estimates for the end of the decade.

The 2024 Artificial Intelligence Strategy contemplates reaching 2,500 MW of computing power by 2030, equivalent to an electrical demand of between 3,500 and 4,000 MW. That is to say, the permits already granted for data centers approximately triple the expected electrical demand for the sector. The comparison does not mean that all that power will be consumed nor that each permit corresponds to an installation that will be built: precisely, part of the applications may not materialize.

The Executive wants to prevent promoters from reserving electrical capacity for projects that are not progressing, preventing other consumers from accessing it. The problem affects both the planning of networks and the competition for a limited resource. If infrastructures are sized to meet a demand that ultimately does not appear, unnecessary investments may be made; if all applications are granted, the pressure on the system could hinder the connection of other industries.

The CNMC shares that concern. Its warning, therefore, does not equate to a rejection of regulation, but rather a call to find a balance between market organization, project viability, and competition.

80% of electricity, backed by new renewable generation

The draft royal decree promoted by the Ministry for the Ecological Transition introduces specific requirements for energy and environmental sustainability, in addition to conditions for resilience and digital sovereignty. One of the most controversial obligations is that data centers must back at least 80% of their electrical consumption with new renewable generation, with hour-by-hour accreditation. The proposal also includes requirements for energy and water efficiency and conditions regarding who operates the facilities and where the data related to their operation is maintained.

The logic of the Government is that the growth of infrastructure that consumes electricity intensively should not compromise energy and environmental objectives. The Executive wants the digital deployment to be accompanied by new renewable capacity, to reduce the impact of installations, and for the data to be subject to European legal guarantees.

For operators, however, the combined effect of the requirements can raise costs and complicate planning. Data centers are designed with long investment horizons: before becoming operational, their promoters may have committed land, financing, equipment, construction, and energy agreements. Modifying the conditions during the development of a project can force a review of its economic calculations and timelines.

SpainDC argues that the proposed demands may place Spain in a less competitive position than that of other European countries. This warning expresses the position of the employers' association and should be contrasted with the actual conditions of alternative markets and with the impact that the approved text ultimately has.

The CNMC calls for moderating the toughest requirements

The debate has taken on a new dimension with the report that the CNMC approved on September 22. The agency recommends reviewing several elements of the project and warns that some obligations could distort the market, generate excessive costs, and hinder the viability of certain investments.

Among the questioned aspects are the rigidity of the renewable coverage obligation, its hourly correlation, compliance deadlines, and certain criteria for energy and water efficiency. The CNMC also proposes reviewing the surcharges planned for cases of non-compliance. Its recommendations are not binding: it is up to the Government to decide what changes to incorporate before approving the regulation.

The regulator thus puts a central issue on the table for the design of the regulation: how to prevent environmental and energy obligations from becoming disproportionate barriers to the entry of new operators. The requirement for new renewable generation can drive clean investments, but its application must take into account development timelines, the availability of projects, and the capacity of promoters to contract or build that generation.

The dispute is not limited, therefore, to choosing between sustainability and investment. It also affects how the costs of the energy transition are distributed, what conditions digital infrastructures must meet, and to what extent regulation can adapt to a rapidly expanding sector.

The pending question: which projects are abandoning Spain

The figure of 1,600 MW confirms that there are renunciations of electrical permits, but it does not allow knowing their final economic impact. It is not known how many installations are behind the withdrawals, what degree of development they had reached, or whether their promoters have decided to abandon Spain, postpone their plans, or renounce capacity reservations that they did not need.

This distinction is fundamental. If the renunciations correspond to speculative projects that were never going to be built, regulation could free up resources for investments with greater execution guarantees. If, on the contrary, they affect advanced initiatives that desist due to the tightening of conditions, Spain could lose opportunities in the international race to attract artificial intelligence infrastructures.

The next update of the CNMC data, the Ministry's response to the regulator's recommendations, and the changes incorporated into the royal decree will allow for better measurement of the consequences. It will also be necessary to contrast the warnings of the employers' association with concrete information from the affected promoters and with data on investment that has actually been canceled or relocated.

For now, the evidence outlines a conflict between two legitimate objectives: preventing electrical permits from being blocked by projects that are not executed and maintaining a sufficiently competitive framework to attract technological investments. The unknown is no longer just how much capacity is being freed up, but whether the Government will manage to organize the market without jeopardizing viable projects. That will be the decisive measure of success —or of the limits— of the new regulation.

 

More key points, information and questions with FREN

AI-GENERATED CONTENT

What is the current parliamentary status of the royal decree on data centers and what are the next steps for its final approval?

The so-called royal decree on data centers has no parliamentary status because it has not yet reached the Cortes nor is it expected to do so: it is processed as an ordinary regulatory royal decree, not as a royal decree-law. This means that, as of today, the text is in an advanced administrative phase within the Government, following the public hearing and information phase and prior to its final approval by the Council of Ministers and its publication in the Official State Gazette (BOE).

What regulation it is and its current stage

The draft royal decree regulates the requirements for energy and environmental sustainability, resilience, and digital sovereignty of data centers connected to the electrical grid. It develops the mandate included in Royal Decree-law 7/2026, which ordered setting specific conditions for these infrastructures in order to align their deployment with the expansion of renewable generation and avoid tensions on the electrical system.

According to official information from the Ministry for the Ecological Transition and the Demographic Challenge (MITECO), the text was subjected to a public hearing and information process on an urgent basis, with an abbreviated period for submitting comments. The consultation documentation — including the full draft of the decree — is available on MITECO's public participation page, where the procedure is marked as already closed.See hearing file

Meanwhile, press releases from MITECO itself and the Ministry for Digital Transformation explain that the decree is being processed with urgency and that the Government's declared political objective is to approve it “shortly” and before the general elections on November 29, so that it can be published in the BOE during this legislature.MITECO noteDigital Transformation note

Economic press and the newspaper Demócrata add that the CNMC report on the project has already been debated and endorsed in the plenary of the body, and that the text is in a phase of internal review among ministries to integrate comments and technical observations before being sent to the Council of State.Demócrata 10/08/2026

Parliamentary implications

Since it is an ordinary regulatory royal decree (not a royal decree-law), the procedure is purely governmental:

  • It is not registered as a bill in the Congress or the Senate.
  • There is no validation or repeal vote.
  • It does not go through committee, commission, or Plenary.

Parliamentary control over this regulation will be subsequent, through debates, non-legislative proposals, motions, or possible legislative initiatives that could modify its legal framework, but the act of approval of the decree corresponds exclusively to the Council of Ministers.

Next steps until final approval

Based on the available information, the remaining process can be summarized as follows:

  • Closing of the comment phase: the public hearing and information period has already ended. The Administration must analyze the contributions received (companies, autonomous communities, employers' associations such as SpainDC, NGOs, etc.) and decide which are incorporated into the text.
  • Completion of mandatory reports: the file must integrate and, if applicable, complete the CNMC reports, those from the affected ministries, and the Office of Coordination and Regulatory Quality.
  • Opinion of the Council of State: before approving a royal decree of this type, it is customary to seek the opinion of the Council of State, which evaluates its legal adequacy, regulatory technique, and coherence with the legal system. This report is not binding, but the Government usually complies with its observations or explains why it departs from them.
  • Approval by the Council of Ministers: once the file is closed (final text + impact report + reports), the royal decree is submitted to the Council of Ministers for formal approval.
  • Publication in the BOE: once approved, the decree is ordered to be published in the Official State Gazette. Only at that moment does the regulation legally exist.
  • Entry into force: the draft foresees a deferred entry into force after publication (for example, twenty days), although the exact period will depend on the final wording. From that date, the new obligations will begin to apply to data centers and projects in process, with the transitional periods established.

In summary, today the data center decree is in a pre-approval phase within the Government, without parliamentary processing, and the key milestones remaining are the completion of mandatory reports, the opinion of the Council of State, approval by the Council of Ministers, and publication in the BOE, after which it will come into force under the terms established in its final provision.

What are the competencies and functions of the Ministry for the Ecological Transition in relation to the regulation of technological infrastructures?

The Ministry for the Ecological Transition and the Demographic Challenge (MITECO) is the competent department, within the scope of the General State Administration, to propose and execute the Government's policy on energy, climate change, environment, water, and demographic challenge. This definition is systematically set out in Royal Decree 503/2024, which develops its basic organic structure, and in various sectoral regulations, such as the Law 7/2021 on climate change and energy transition.

General framework of competencies

According to article 1 of Royal Decree 503/2024, MITECO is responsible for:

  • Drafting state legislation on energy, climate change, environment, water, coasts, and biodiversity.
  • Developing national energy policy and measures to ensure supply, decarbonization, and economic-financial sustainability of the electrical and gas systems.
  • Defining and executing the energy transition strategy and policy addressing the demographic challenge.
  • Coordinating with autonomous communities, local entities, the European Union, and international organizations in all these matters.

Organizationally, the Secretary of State for Energy and the Directorates-General for Energy Policy and Mines and for Energy Planning and Coordination concentrate most of the competencies related to energy technological infrastructures.

Energy networks and technological infrastructures

Regarding the regulation of energy technological infrastructures (networks, large facilities, interconnections), MITECO performs functions of:

  • Infrastructure planning: defines, together with system operators, the indicative and binding planning of energy infrastructures (arts. 2 and 3 of RD 503/2024), integrating renewable and climate neutrality objectives set in Law 7/2021 and in the National Integrated Energy and Climate Plans.
  • Sectoral regulation and planning: the Directorate-General for Energy Policy and Mines drafts basic regulations on transport, distribution, electricity and gas markets, including technical, safety, and service quality conditions.
  • Administrative authorizations: processes and resolves, when the competence is state-level, authorizations for generation, transport, storage, and evacuation infrastructures, as well as associated sanctioning proceedings.
  • Technical and economic supervision: analyzes market functioning, proposes regulated remuneration methodologies, and supervises compliance with technical obligations in state-dependent facilities.

At the same time, MITECO promotes network modernization (e.g., incorporation of dynamic line capacity, network codes, and advanced technical requirements) through regulatory projects and aid programs, as reflected in multiple press releases and ministerial orders on electrical system reinforcement, smart grids, and flexibility.

Energy storage and hydrogen

Sectoral regulations and regulatory practice show that storage and hydrogen are considered key pieces of the technological infrastructure of the energy transition. MITECO:

  • Integrates specific storage objectives in energy planning and in the Energy Storage Strategy, derived from Law 7/2021.
  • Regulates access, connection, and participation conditions for storage (pumped hydro, batteries, thermal storage, etc.) in the system and markets, and processes state-competent projects.
  • Designs calls and regulatory bases for aid to innovative storage projects and to the manufacture of equipment and components linked to these technologies.
  • Regarding renewable hydrogen and renewable gases, sets objectives, promotes hydrogen valleys and corridors, participates in defining the backbone network, and coordinates sustainability and climate compatibility requirements.

These actions are supported by specific regulations (royal decrees, TED orders) and planning instruments derived from Law 7/2021.

Digitalization, energy data, and data centers

Digitalization appears in Law 7/2021 as one of the vectors of decarbonization (article 6). The Government, with a central role for MITECO, must promote:

  • The incorporation of digital technologies into the energy system, smart grids and cities, and natural capital management.
  • The use of artificial intelligence and other technologies to improve energy efficiency, demand management, and renewable integration.
  • Actions to reduce the climate impact of the digital economy.

In parallel, MITECO co-leads the regulation of data centers from the energy perspective: requirements for water and energy efficiency, majority coverage of consumption with new renewable generation, and grid access conditions. These regulations, under processing through royal decree projects and public consultations, seek an orderly deployment of energy-intensive data centers, coordinated with network capacity and renewable objectives.

Environmental assessment and territorial cohesion

Almost all technological infrastructures of the ecological transition entail territorial and environmental impact. MITECO, through the Secretary of State for Environment and its directorates-general, assumes:

  • Environmental impact assessment of state-competent projects (e.g., large storage facilities and their evacuation infrastructures), applying criteria set in Royal Decree 503/2024.
  • Protection of biodiversity, water, coasts, and sea, harmonizing renewable deployment and natural heritage conservation.
  • Incorporation of the demographic challenge dimension: ensuring technological infrastructures contribute to revitalizing rural areas and a just transition, in line with the Just Transition Strategy and policies of the General Secretariat for the Demographic Challenge.

Overall, MITECO does not directly operate these infrastructures but designs the legislative, regulatory, environmental, financial, and planning framework that conditions their design, location, operation, and contribution to the ecological and digital transition of the Spanish energy system.

Can you detail the specific competencies of the Directorate-General for Energy Policy and Mines and that of Energy Planning and Coordination regarding smart grids and storage? What role does the CNMC have vis-à-vis MITECO in the regulation of hydrogen infrastructures and energy storage? Could you explain what the draft royal decree on data centers requires in terms of energy efficiency and renewable use?

What legal requirements must data centers meet to access the electrical grid according to current regulations?

In Spain, data centers do not have a completely autonomous electrical regime but are integrated into the general framework of access and connection to transmission and distribution networks, to which specific requirements for this type of large demand are being added. Today it is useful to distinguish between: a) the current general framework for access and connection of any large consumer, and b) the specific draft royal decree for data centers, still in processing but which will condition their access and connection rights.

1. Current general framework for access and connection

The basic framework is given by:

  • Law 24/2013, of the Electric Sector, which recognizes the right of all consumers to access and connect to the networks under objective, transparent, and non-discriminatory conditions and establishes the distribution of competencies.
  • Royal Decree 1183/2020, on access and connection to transmission and distribution networks, which develops article 33 of Law 24/2013.
  • CNMC Circular 1/2024, which establishes the methodology and conditions for access and connection of demand installations.

For a data center, these texts imply, in summary:

  • Access and connection permits: before connecting, an access permit (use of network capacity at a specific node) and a connection permit (technical conditions for coupling at the chosen point) must be obtained. The application is submitted to the network manager (Red Eléctrica for transmission or the distributor for distribution) with data on power, location, and demand characteristics.
  • Criteria and causes for rejection/denial: the manager must apply the objective criteria set by Royal Decree 1183/2020 and Circular 1/2024 (temporal precedence, published capacities, system security limits, specific reasons for rejection and denial, obligation to justify and return guarantees when the cause is not attributable to the applicant).
  • Financial guarantees: for demand requests, the regulation requires depositing a financial guarantee per requested power (the current reference is €40/kW for certain cases, according to recent regulatory development). This guarantee is lost totally or partially if the project does not progress or the request is made at nodes without available capacity contrary to published information.
  • Authorizations and contracts: even with access and connection permits granted, connection can only be materialized when administrative authorizations for the associated electrical infrastructure have been granted, necessary network works have been executed, and the access contract with the distributor or transporter and the supply contract with a retailer have been formalized.
  • Technical requirements: European network codes for demand connection, Order TED/749/2020 on technical connection requirements, and operation procedures approved by MITECO and CNMC must be met (protections, remote measurement, remote control, voltage quality, etc.). For large loads connected at high voltage, reinforced requirements for observability, real-time measurement sending, and network manager intervention capacity apply.

Additionally, the CNMC has regulated flexible access permits for demand (resolution of 08/11/2026): these allow connecting new large consumers even at nodes without firm capacity, in exchange for accepting power limitations at certain hours or network situations. A data center may opt for this regime, subject to its installation being prepared to reduce consumption when required by the operator.

2. Specific draft for data centers

On top of this general framework, the Government is processing a Draft Royal Decree on energy sustainability, environmental, resilience, and digital sovereignty requirements applicable to data centers, derived from a mandate of Royal Decree-law 7/2026. Although not yet approved, its design is clear and it is proposed as a condition for the access and connection rights of large data centers (general threshold: access power ≥ 1 MW):

  • Reinforced renewable consumption: until renewable generation exceeds 90% of the mix, the center must prove that at least 80% of its hourly consumption is backed by renewable generation produced in that same hour, with additionality requirements (each new MW of demand must be accompanied by a new MW of renewable installed in the previous 18 months, via self-consumption or PPA).
  • Conditioning of access and connection: projects must prove compliance with these requirements to obtain or maintain access and connection rights. Non-compliance will result in increasing surcharges on charges and tolls and, ultimately, in loss of access rights.
  • Energy and water efficiency: the highest level (category A) of the future European data center labeling (Delegated Regulation (EU) 2024/1364) will be required in indicators such as PUE and WUE, once it comes into force.
  • Digital sovereignty: the center operator must be established in the EU and data, metadata, and operation records must remain within the community territory; serious non-compliance with these conditions may also lead to withdrawal of access and connection rights.

Overall, a data center wishing to access the grid must today comply with the entire general access and connection regime (Law 24/2013, Royal Decree 1183/2020, Circular 1/2024, guarantees, technical requirements, and authorizations) and, likely soon, also be subject to this new block of specific obligations regarding renewables, efficiency, water, and digital sovereignty, whose compliance will be directly linked to granting and maintaining its access and connection rights.

Can you detail what specific documentation must be submitted in the access and connection application for a data center over 50 MW? How will flexible access permits work in practice for a large data center and what operational risks do they imply? What differences exist between the requirements proposed in the Spanish draft royal decree for data centers and the demands being debated at the European Union level?

Play

Test your knowledge with FREN!

How much do you know about this topic? Answer the following 3 questions.

What is the electrical capacity that data center promoters have given up according to the CNMC?

Question 1 of 3

What percentage of the projected electrical demand for the sector in 2030 does the capacity of surrendered permits represent?

Question 2 of 3

What is one of the most controversial obligations of the royal decree for data centers?

Question 3 of 3