Iberdrola, through its British subsidiary ScottishPower, has reached a new milestone in the development of the offshore wind farm "East Anglia 3", driven together with Masdar and considered the largest of the group in this technology. The complex, with an installed capacity of 1,400 megawatts (MW) and valued at 4 billion pounds sterling (about 4.676 billion euros), has completed the installation of the 95 foundations off the coast of Suffolk (United Kingdom), the company reported.
Weighing between 1,200 and 1,800 tons, with a height of between 67 and 84 meters and a diameter of up to 10.6 meters, the monopiles used are the largest that have been placed from a jack-up vessel in Europe.
In parallel, the assembly of the 95 transition pieces, 20 meters high, eight meters in diameter, and weighing over 400 tons, has also been completed.
Iberdrola's British subsidiary noted that, with the installation of the turbines already underway, both onshore and offshore works will continue at a good pace over the coming months. This will allow "East Anglia 3" to enter full commercial operation by the end of this year, providing 1.4 gigawatts (GW) of clean energy from domestic sources to the UK's electrical system.
"East Anglia 3" is the second project to be launched within the strategic alliance of 15 billion euros signed between Masdar and Iberdrola, and the first to be developed with ScottishPower in British territory.
The investment of nearly 2 billion pounds sterling (about 2.338 billion euros) in the UK's supply chain includes the design of the foundations by Wood Thilsted, the manufacturing of the turbine blades at the Siemens Gamesa plant in Hull, the chartering of vessels to NR Marine Services and OEG, based in Norfolk, as well as the work of the consultancy Partrac, specialized in meteorology, oceanography, and seabed analysis.
The "East Anglia 3" project is supporting 2,300 jobs during the construction phase and will generate around a hundred permanent jobs in the east of England.
With its capacity of 1.4 GW, the park will produce enough renewable energy to supply more than 1.3 million homes, reinforcing the energy supply security of the United Kingdom.
"TRUE TRIUMPH OF ENGINEERING"
The CEO of ScottishPower Renewables, Charlie Jordan, highlighted that the completion of the installation of the project's foundations "is a true triumph of engineering." "Just look at the figures - more than 200,000 tons of steel precisely anchored in a seabed the size of almost 43,000 football fields - to get an idea of what we have achieved so far. It's impressive," he said.
He also emphasized that ScottishPower Renewables and Masdar are not only supplying renewable electricity from domestic production to millions of homes, but also "are driving a cleaner, greener, and more prosperous future for all, with nearly £2 billion invested in the domestic supply chain, thousands of jobs supported during construction, and around 100 jobs created during the lifetime of the wind farm." "This not only generates a positive impact but also creates a powerful legacy," he added in this regard.
For his part, the CEO of Global and UK Offshore Wind at Masdar, Husain Al Meer, stated that the progress on the "East Anglia 3" project reflects "the strength of the collaboration with ScottishPower and the expertise of the project team and contractors, particularly Seaway7, working together to build one of the largest offshore wind farms in the UK."