Regulatory Risk: the five energy decisions in the air for the 29N

The electoral advance comes with outstanding energy files still pending completion, from the auctions of the capacity market and cogeneration to the regulation of data centers.

fotonoticia 20261007132003 1920

fotonoticia 20261007132003 1920

Add DEMÓCRATA to Google

Ask FREN

Published

Last updated

5 minutes

Most read

Elecciones 29N · Encuestas

La media de las encuestas

Media a 18 de noviembre de 2026 · 17 institutos

  • PP31,4 %
  • PSOE27,4 %
  • Vox19,0 %
  • Frente Amplio6,1 %
  • ERC2,4 %
  • SALF2,0 %
01020304050ene 2024jul 2024ene 2025jul 2025ene 2026jul 2026

Media del último estudio de cada instituto en 30 días y su evolución semanal desde el 23J. Partidos con al menos un 2 %.

Todas las encuestas

Elecciones generales del 29 de noviembre · Demócrata

The dissolution of the Cortes due to the call for the general elections on the next 29th of November comes with several decisive files for the energy sector pending completion of their processing or resolution.

In the air are, for example, the more than 17 billion euros of investment planned in the transport network planning until 2030, the new rules on data centers, the deployment of the capacity market, or an auction of 600 MW for cogeneration facilities.

For the listed energy, industrial, and real estate companies involved, the decisions condition everything from new sources of remuneration to the location of investments and the possibility of connecting new projects to the grid.

Capacity market: with regulation but without auction

The Government approved in September the creation of the electrical capacity market, a mechanism aimed at ensuring that the system has sufficient firm capacity even when renewable generation cannot cover demand. Order TED/966/2026 is already in force, but for its effective functioning, it is necessary for the Secretary of State for Energy to call for auctions.

Before, Red Eléctrica must calculate the needs for firm capacity and the corresponding coefficients, and the proposal must go through public information and receive a report from the CNMC, for which it has a maximum of 20 working days.

The mechanism will allow certain facilities to charge for committing to be available when the system needs them. Electric producers, storage facilities, consumers, and demand aggregators will be able to participate. For new investments, the main auctions are reserved for renewables, storage, or demand, while existing facilities can compete under the conditions established in the order.

Involved listed companies: Among the listed companies with potentially interested assets are Iberdrola, Endesa, Naturgy, and Acciona Energía, especially due to their generation and storage portfolios. Their effective participation and the income that each company could obtain will depend on the specific conditions of the auctions and the assets that are enabled.

Redeia occupies a different position. Through Red Eléctrica, it acts as the system operator and will be a central piece in determining the coverage needs on which the calls will be built. It is not a potential beneficiary of the remuneration under the same conditions as the generators.

Cogeneration: 600 MW expected in auction

Ecological Transition is preparing for December a 600 MW high-efficiency cogeneration auction, the first of two planned to renew or incorporate a total of 1,200 MW between 2026 and 2027. The proposal remained in public hearing until last September 15.

Of the 600 MW planned for the first call, 505 MW correspond to gas installations and 95 MW to biomass, distributed across ten different products. The mechanism will allow both renewing existing installations and developing new ones and will grant the awardees a specific remuneration regime.

Among the listed companies with exposure to the industrial and energy sector are groups like Repsol, in addition to industrial companies that use or may be linked to cogeneration installations. In biomass, Ence is one of the main Spanish operators of generation with this technology, although not every biomass plant is a cogeneration installation nor can it be taken for granted that it will participate. Naturgy, Endesa or Iberdrola may also appear through their energy activities.

Data centers: access to the network

The file facing a more evident race against the electoral calendar is the decree that will impose new energy, environmental, and digital sovereignty requirements on data centers with an access power equal to or greater than 1 MW.

The dispute has a physical reason: the capacity of the network is limited. Since the end of 2023, Red Eléctrica has granted more than 6 GW of access capacity to data centers in transport, and since 2020, distribution networks have granted around another 6 GW. Meeting all the detected demand would require dedicating a significant part of the planned investments in the networks to these installations.

The draft aims to use criteria of energy efficiency, water consumption, renewables, resilience, and digital sovereignty to organize the development of these infrastructures. The design initially submitted for public consultation included strong requirements on covering consumption with new renewable generation, one of the most questioned elements by the sector and subject to changes in the final text.

Listed companies involved: Merlin Properties has a direct bet on data centers, just like ACS, while Iberdrola and Endesa are involved as electricity suppliers and distribution network operators. For Redeia, the proliferation of data centers also implies strong pressure on the planning and management of the transport network.

Transport network: more than 17 billion to be decided

The fourth major file is the Planning of the Electric Energy Transport Network with a horizon of 2030, an essential decision to determine where industrial demand can grow, new renewable generation can connect, or storage can develop in the coming years.

The initial proposal contemplated about 13.6 billion euros, but the Government raised the figure in September to more than 17 billion after analyzing 2,566 objections. This is 30% more than initially proposed and, according to Ecological Transition, 144% more than the current planning.

Listed companies involved: the most directly affected is Redeia, whose subsidiary Red Eléctrica is a transporter and system operator. The map is also decisive for Iberdrola, Endesa, Naturgy, Acciona Energía and Solaria, because the availability of capacity conditions where new generation, storage, or demand projects can connect. In the case of Iberdrola and Endesa, there is also a second aspect due to their distribution activity, although the transport planning and distribution investment plans are distinct instruments.

Self-consumption, storage, and repowering

The fifth file groups several changes that Ecological Transition brought to public consultation urgently in July through a draft Royal Decree to facilitate industrial self-consumption, repowering of renewable parks, storage, and access and connection to the grid.

One of the main novelties is the creation of procedures to release and allocate capacity in nodes reserved for tender. A part would be allocated to the repowering of renewable facilities, especially old wind farms, so that equipment can be replaced and production increased by taking advantage of already existing connections. Another avenue would reserve capacity for renewable self-consumption projects associated with large industrial facilities.

The project also introduces measures to promote storage. Reversible hydroelectric plants could incorporate new power electronics solutions and solar thermal plants could expand their solar field and install thermal storage. It also proposes to incorporate dynamically capable lines systems to better utilize existing networks and reduce some administrative procedures.

Listed companies involved: it is of particular interest to Iberdrola, Endesa and Acciona Energía, due to their renewable portfolios and possibilities for repowering and storage. Solaria may be affected by access and connection rules and by the development of storage associated with renewable generation, although the extent will depend on its specific projects. For Redeia, the modifications related to capacity utilization and network operation have a different impact, linked to its role as system operator.

There is also an industrial derivative: reserving capacity for self-consumption linked to large consumers may modify energy costs and investment decisions of electro-intensive factories.

More key points, information and questions with FREN

AI-GENERATED CONTENT

At what stage is the parliamentary processing of the electric transmission network planning with a 2030 horizon?

The planning of the electric energy transmission network with a 2030 horizon is not being processed as a law in the strict sense in the Congress or the Senate. It is an administrative planning by the Government, whose approval corresponds to the Council of Ministers according to article 4 of Law 24/2013 of the Electric Sector, and which is supported by phases of consultation and public hearing, technical reports, and parliamentary control, but not by an ordinary legislative procedure with a bill or legislative proposal.

What related parliamentary initiatives exist?

In the General Courts, there is no specific bill or legislative proposal titled “Electric Transmission Network Planning Horizon 2030.” What does exist is:

  • An initiative in the Senate (file (15)810/000422, 15th Legislature), which is a certification of the agreement of the Plenary of the Tomelloso City Council regarding the modification of specific aspects of the Transmission Network Development Plan 2021‑2026. Its processing concluded on February 2, 2024, without substantive votes on the technical content of the plan, and it is now closed.
  • Various control and political debate initiatives (questions, appearances, motions) in which groups such as PNV, PP, or territorial parties discuss the 2021‑2026 planning and the 2030 proposal, but this does not translate into an autonomous legislative initiative on the planning.

That is, from a strictly procedural point of view, there is no “2030 planning law” under parliamentary processing; what exists is political control over an administrative file whose final approval is the Government's competence.

Status of the 2030 planning file in the administrative phase

Within the Executive sphere, the file of the “proposal for planning the electric energy transmission network for the 2030 horizon” is clearly identified:

  • The Ministry for the Ecological Transition opened a public hearing, consultation, and information procedure on that proposal and its strategic environmental study, with participation from administrations and interested persons, between October 10, 2025 and December 16, 2025. The information is available on the MITECO website (public hearing details).
  • The press release “MITECO launches the Electric Planning Proposal with a 2030 horizon to public hearing” describes how an initial proposal for the development of the transmission network with a 2030 horizon is submitted to public hearing, with an estimated investment of about 13.6 billion euros and a strong focus on industrial demand and storage (MITECO note).
  • Earlier notes, such as “Sara Aagesen announces the general lines of the 2030 Electric Planning Proposal,” in September 2025, explain the framework of the proposal and link it to a draft royal decree on network investment plans, but still place the core of the planning within the Government's administrative scope and the system operator (Moncloa note).

According to this documentation, as of the latest available references, the 2030 planning file is in an advanced phase of administrative preparation and environmental evaluation, but it is not yet definitively approved.

Role of Parliament in this planning

Law 24/2013 foresees that the transmission network planning has a component of parliamentary consultation, but maintains formal approval in the hands of the Council of Ministers. This translates into:

  • The Congress and the Senate can debate the planning in committees and control sessions, and issue political opinions.
  • The current planning (2021‑2026) was “submitted” to Congress before its governmental approval, but not processed as a law. For the 2030 horizon, the available information points to the same pattern: debates and questions, but without a specific legislative file.

Conclusion on the “parliamentary processing”

With the available information, the situation can be summarized as follows:

  • There is no bill or legislative proposal for “electric transmission network planning horizon 2030” under processing in Congress or Senate; what exists are control initiatives and political pronouncements on the planning content.
  • The 2030 planning file is in an advanced administrative phase: initial proposal prepared, submitted to public hearing and strategic environmental assessment, pending closure of allegations and obtaining the necessary technical and CNMC reports before approval by the Council of Ministers.
  • Therefore, if strictly asked about “parliamentary processing,” today only political control and debate can be spoken of, not a legislative process with consideration, committee, report, and votes on a specific law text.
Could you detail what formal steps remain before the Government can definitively approve the electric planning with a 2030 horizon? What differences exist between the already effective 2021‑2026 planning and the 2030 planning proposal regarding investments and priorities? What specific role are the different parliamentary groups playing in the debate on the 2030 electric planning?

What are the powers and functions of the Secretary of State for Energy in the process of calling capacity market auctions?

In the new Spanish capacity market, the Secretary of State for Energy (SEE), integrated within MITECO, is the key political and administrative body: it designs the regulatory framework together with the Ministry, formally activates the auctions through a resolution published in the BOE, and directs their development, while Red Eléctrica (system operator) technically manages the auctions and the CNMC exercises regulatory and market supervision.

1. Regulatory design of the capacity mechanism

The capacity market is structured through a ministerial order from MITECO, subject to consultation and public hearing (draft order of 12/18/2024 and final order announced in September 2026). In this phase, the SEE effectively performs the following functions:

  • Promotion and coordination of the order text that creates the capacity market in the peninsular electric system, aligning it with European regulations (Regulation (EU) 2019/943 and State aid control) and the Implementation Plan submitted to the European Commission.
  • Definition of the mechanism architecture: who can participate (generation, storage, demand, and aggregators), product types (firm capacity), contract time horizon, and remuneration structure (pay-as-bid auctions, €/MW/year).
  • Determination of the distribution of institutional roles, setting in the order what corresponds to the SEE itself, the system operator (REE), and the CNMC (supervision and control of the capacity service).
  • Establishment of the financial framework of the mechanism (who pays, how it is passed on via tolls or charges, and in which time slots the cost is concentrated).
2. Planning and parameterization of the auctions

Based on the ministerial order and the coverage analyses carried out by REE, the SEE has competencies in the planning of the auctions that materialize the capacity market:

  • Determining the types of auctions held (main medium and long-term, annual adjustment, and transitional) and their service provision horizon.
  • Setting, at the system operator's proposal, the volume of firm capacity to auction according to the supply security needs detected five years ahead.
  • Establishing the general parameters of the calls: environmental requirements (e.g., CO₂ emission limits), firmness and flexibility demands, maximum contract duration, eligibility criteria for new investments, etc.
3. Formal call of the auctions

The order foresees that auctions are activated through a resolution by the holder of the Secretary of State for Energy, published in the BOE. This call resolution specifies:

  • The capacity product being auctioned (auction type, service period, target capacity).
  • The detailed calendar (deadlines for submitting offers, auction date, capacity obligation start date).
  • The participation requirements and the technical and economic documentation agents must provide.
  • The guarantee regime and, if applicable, reserve prices or limits for reckless bids.

This scheme is consistent with other SEE competencies already in force in related matters, such as the call for demand access capacity tenders in the transmission network under Royal Decree 1183/2020 and Royal Decree-law 8/2023, where the Secretary of State calls and sets the procedure bases by resolution.

4. Relationship with the system operator and the CNMC

In the capacity market operation, the SEE does not directly manage the auction: that is REE's function as system operator. However, the Secretary of State:

  • Requests and uses REE's technical analyses to decide volumes and auction design.
  • Approves or promotes the approval of operation procedures specific to the capacity service through SEE resolutions, which develop the ministerial order.
  • Coordinates with the CNMC, which retains its functions of regulation, market supervision, and approval of methodologies on wholesale markets and balancing services. The consulted documentation does not attribute hierarchical direction capacity of the CNMC to the SEE, but a coordination framework.
5. Auction results and mechanism supervision

The available official documentation clearly emphasizes that:

  • REE manages the auctions and the contracting of the capacity service.
  • REE and the CNMC verify and inspect the correct provision of the capacity service.

Regarding approval of results, the consulted texts confirm that the SEE calls the auctions and defines their bases, but do not expressly describe a differentiated competence of “approval” of the results beyond the official publication of the awardees when established by each order or resolution.

Finally, as the political body responsible for energy policy, the SEE exercises a monitoring and review function of the capacity mechanism: it can propose modifications to the order and auction parameters, and participates in the dialogue with the European Commission on the mechanism's evaluation and its compatibility with State aid rules.

Can you specify what the ministerial order of the capacity market says about who exactly calls each type of auction and how its volume is set? What technical role do Red Eléctrica and the CNMC play within each specific capacity market auction? How does the Secretary of State for Energy coordinate with Brussels in the approval and review of this capacity mechanism?

What legal requirements must installations meet to participate in capacity and cogeneration auctions according to current regulations?

In the current state regulations, the requirements for an installation to participate in auctions related to generation capacity and cogeneration/renewables are structured around two main blocks: the renewable energy economic regime (REER) and the remuneration framework for renewables, cogeneration, and waste. Although specific details are set in each call, there is a relatively stable set of minimum legal requirements.

1. General framework of renewable auctions with specific remuneration

The core of current renewable auctions is Royal Decree 960/2020, of November 3, which regulates the economic regime of renewable energies for electricity production installations, and its development through Order TED/1161/2020, of December 4, which regulates the first auction mechanism and an indicative calendar 2020‑2025.

Generally, to participate in these auctions, installations (or their promoters) must meet requirements such as:

  • Being a renewable generation installation (or hybrid with storage) included in category b) of Royal Decree 413/2014, of June 6, on production from renewables, cogeneration, and waste.
  • Minimum administrative status: Order TED/1161/2020 and the call resolutions require demonstrating a certain project maturity level, typically:
    • Having receipt acknowledgment or concession of access and connection permits to the grids, according to CNMC Circular 1/2021 on access and connection.
    • Having, within the deadlines set by the call, administrative construction authorization or equivalent.
    • Meeting the execution milestones indicated (final identification of the installation, commissioning before the deadline, etc.).
  • Registration in the specific REER registry:
    • First in pre-assignment status, linked to the auction result.
    • Subsequently in operational status, once compliance with technical and administrative requirements and commissioning is accredited.
  • Financial guarantees: the framework sets guarantees linked both to auction participation and registry inscription:
    • Guarantee prior to the auction (e.g., amounts per kW of offered capacity), configured as an essential participation requirement.
    • Guarantee associated with pre-assignment registration and transition to operation, aimed at ensuring real project execution and compliance with the minimum auctioned energy.
  • Concentration limits: a maximum volume assignable to the same company or business group per auctioned product is established to guarantee competition and avoid excessive concentration of results.
  • Technical and market requirements:
    • Real possibility to sell energy in the market (day-ahead/intraday market and, if applicable, balancing services), according to market rules (e.g., those approved by CNMC through resolutions in 2021, 2023, and 2024).
    • Compliance with system operation and measurement, control, and communication rules required by the system operator and sector regulation.
2. Cogeneration, renewables, and waste: remuneration framework and auctions/calls

Installations of cogeneration and waste are generally governed by Royal Decree 413/2014 and ministerial orders updating remuneration parameters for typical installations, such as Order TED/171/2020, of February 24, and its successive updates (Orders TED/995/2022, TED/1232/2022, TED/1295/2022, TED/741/2023, TED/53/2026, among others).

In the case of auctions or competitive programs specifically aimed at cogeneration or substitution of fossil fuels by renewables (e.g., within the Recovery Plan, such as Order TED/641/2023 for renewable electricity and heat projects), usual installation requirements include:

  • Fit within a typical installation or the technological categories defined in the regulation (biomass, biogas, high-efficiency cogeneration, waste, etc.).
  • Energy and efficiency criteria:
    • Demonstrate minimum energy efficiencies and, in cogeneration, parameters to consider it high efficiency according to European and national regulations.
    • In some programs, prove the effective substitution of fossil fuel-based production by renewable energy.
  • Comparable administrative status to that described for renewable electricity: access and connection permits, administrative authorizations, compliance with time milestones, and capacity to obtain registration in the applicable remuneration regime registries.
  • Compatibility with State aid: the regulatory bases usually remind the obligation to respect the European aid framework (energy and climate aid guidelines, Regulation (EU) 2019/943, Directive (EU) 2018/2001, etc.), which translates into:
    • Open, transparent, competitive, and non-discriminatory procedures.
    • Limitation of aid intensity and exposure of the installation to the market (obligation to participate in the wholesale market).
3. Common horizontal requirements

Besides the specific requirements of each auction, any installation intending to participate must comply with a series of transversal legal demands:

  • Compliance with environmental regulations: environmental impact assessment when applicable, integrated or sectoral environmental authorizations, and for certain technologies, respect for sustainability and emission reduction criteria (e.g., Royal Decree 376/2022 on biofuels, bioliquids, and biomass fuels).
  • Compliance with electricity market regulations: registration in the administrative registry of production installations, contracting a representative, compliance with grid codes and CNMC regulations on wholesale market and system operation.
  • Economic and technical solvency, usually demonstrated by providing guarantees, prior experience, or the promoter's technical capacity, as established in each call's bases or resolution.

In summary, to participate today in renewable capacity or cogeneration/renewables/waste auctions, the installation must be legally framed in the eligible categories, have advanced administrative processing (grid permits, authorizations, registry), comply with technical connection and operation requirements, provide the required financial guarantees, and respect both environmental regulations and the European framework of State aid and electricity market.

Can you detail the specific administrative maturity requirements (permits and authorizations) demanded in the latest renewable auction calls? What differences exist between the participation requirements of a cogeneration installation and a photovoltaic plant in these auctions? How are financial guarantees and penalties structured if an awarded installation fails to meet the committed execution milestones?

Play

Test your knowledge with FREN!

How much do you know about this topic? Answer the following 3 questions.

What amount of investment is planned in the transport network planning until 2030 after the latest review?

Question 1 of 3

What mechanism was approved in September to guarantee firm capacity in the Spanish electricity system?

Question 2 of 3

Which company acts as system operator and is key to determining coverage needs in upcoming calls?

Question 3 of 3