The representatives of the Council (Member States) and the European Parliament have reached a political agreement to speed up the processing of renewable energy projects, electricity grids, and storage and charging infrastructure. The aim is to set shorter deadlines and allow certain administrative steps to be considered approved if the authorities do not respond within the established time, in order to reduce the delays that today block the deployment of these installations in Europe.
The commitment, reached in the early hours of this Wednesday, is intended to eliminate “unnecessary delays” and facilitate the connection of new plants to the grid, according to the Council. In its view, accelerating these procedures will help to strengthen the European Union’s energy security and reduce dependence on fossil fuels from abroad.
The new provisions set a maximum of three months to grant permits for solar installations and their linked storage systems, excluding hydrogen, and six months for standalone batteries and charging points. In the case of pumped hydropower plants intended for energy storage, the deadline may be extended up to two years.
At the same time, requests to connect these projects to the electricity grid must be resolved within a maximum of three months, extendable to six in justified circumstances. Exceptions, however, are contemplated for isolated or smaller-scale infrastructure, such as those that operate in certain outermost regions.
The agreement will also allow Member States to give priority to renewables and electricity infrastructure by classifying them as of “overriding public interest.” This consideration will facilitate their authorization when they come into conflict with other interests, except in duly justified situations linked to security, defense, or the preservation of cultural heritage.
Another development includes the creation of single digital windows to submit applications and complete all procedures from a single portal, with the intention of simplifying red tape and making it “faster and more transparent.”
Likewise, it introduces the obligation for promoters of renewable energy projects of more than seven megawatts to allocate part of the economic benefits to the local communities that host the facilities or are affected by them, lowering the threshold compared with the initial proposal of ten megawatts. Initiatives driven by renewable energy communities, however, will be exempt from this requirement.
The new rules also provide that certain small-scale solar equipment, storage systems and charging points may be installed without the need for permits when their power does not exceed 200 kilowatts, double the previous limit. Likewise, charging stations of up to one megawatt located on artificial structures will not require administrative authorization.
With this reform, an attempt is made to address the long waiting times that weigh down the European energy sector. According to the data handled by the Council and the Parliament, electricity transmission networks take around ten years to be completed, more than half of which is consumed in obtaining authorizations, while permits for new renewable installations can be extended to up to nine years.
The agreed text will still need the backing of the plenary of the European Parliament and of the Council for its final adoption. From that moment on, member States will have 18 months to transpose these rules into their national legal systems.