The Ministry of Housing has emphasized that the royal decree approved this Tuesday by the Council of Ministers, aimed at streamlining procedures for access, connection and authorization of electrical installations, will make the processing of new residential developments easier and will facilitate urban development for up to three million homes.
In particular, new housing developments may avail themselves of the exemption from the report of the National Commission for Markets and Competition (CNMC) in certain connections, and also benefit from processing through digital advertising in public utility proceedings, as the Ministry of Housing and Urban Agenda has stated.
This initiative adds to the new Planning of the Electric Transmission Network Horizon 2030, validated by the Council of Ministers last Friday, 20 November, which provides for investments to cover 5,957 megawatts (MW) of new residential demand, sufficient capacity to supply electricity to three million homes with a high level of electrification.
The plan includes a total investment of 17,143 million euros with the aim of strengthening the transmission network and responding to 47.4 gigawatts (GW) of additional demand. Of that volume, residential use accounts for 12.6%.
The Community of Madrid groups 3,073 MW of the new residential demand planned, which represents 51.6% of the national total. This reinforcement will make it possible to provide coverage for developments such as Los Cerros, Los Berrocales and Valdecarros. The planning also foresees new housing demand in Andalusia (774 MW), the Comunitat Valenciana (540 MW) and Castilla-La Mancha (364 MW).
Priority of the network for housing developments
The planning document sets out that, of the 301 support positions for the distribution network contemplated, 103 incorporate residential demand. Of these, 40 are reserved exclusively for this use and the remaining 63 are made compatible with industrial-type activities.
In these cases, the priority of supply for residential use is strengthened in the use of the new electrical capacities during the first three years, in order to prevent other activities from displacing that demand during this initial period.
This preference was already included in Royal Decree-Law 7/2026, of March 20, approved to contain the energy and economic impact derived from the conflict in the Middle East. The regulation classifies as high-priority consumer installations the requests for access and connection for real estate development projects for residential use connected to a voltage equal to or greater than one kilovolt.