The power grid and regulation threaten more than half of European 'data centers', according to a report

A report warns that the power grid and regulation threaten more than 50% of European data centers and put €66.9 billion at risk in Spain.

5 minutes

fotonoticia 20261119122329 1920
Add DEMÓCRATA to Google

Published

5 minutes

The long waits to connect to the power grid, which in some cases reach up to thirteen years, together with regulatory uncertainty, call into question the realization of more than 50% of the planned “data centers” in Europe. This blockage jeopardizes the deployment of infrastructure that, only in Spain, could reach mobilizing close to 66,900 million euros by 2030.

These conclusions are set out in the report “La infraestructura de la era de la IA,” prepared in connection with the upcoming summit “The AI Cities Summit Europa” by InfraXmedia. The event will bring together in Zaragoza, on February 3 and 4, 2027, representatives of Public Administrations, energy companies, investment funds, and operators to analyze the future of these facilities.

The study focuses on the gap between announced investments and the real capacity to execute. Although the industry’s forecasts point to fewer than half of the European projects being built, the firm DTCP raises pessimism and argues that “less than 20%” will move forward in the short term.

All of this occurs in a scenario in which Europe has around 16 gigawatts (GW) of installed capacity—compared with the 48 GW of the United States and the 38 GW of China—and barely concentrates 5% of the world computing power intended for artificial intelligence (AI).

To try to close this gap, the European Commission calculates that an investment of up to 600,000 million euros will be needed over ten years, although it warns of a structural grid deficit of close to 19 GW by 2036.

Criticism of the draft law and congestion on the power grid

In the Spanish sphere, companies in the sector point to regulations as one of the major obstacles to taking advantage of the country’s advantageous position. The executive director of SpainDC, Begoña Villacís, warns that the 2026 draft law on data centers, still pending final approval, would equate “as currently worded, to a de facto ban on the sector in Spain,” since it could deter new investments and put at risk projects that are already under development.

Along the same lines, the chief executive officer (CEO) of Templus, Ignacio Velilla, stresses that regulatory uncertainty does not stop demand, but rather “shifts it to other Member States.” This lack of legal certainty is joined by the saturation of the power grid as a key element.

Within the European Union, the timelines for securing a grid connection point vary between three and ten years, reaching up to thirteen in the areas with the highest congestion. For this reason, both operators and energy companies are calling for abandoning the rigid “first come, first served” criterion and prioritizing projects according to their real level of maturity—land availability, permits, financing, and committed customers—applying “use it or lose it” rules that prevent speculative capacity reservations.

The report also warns of increasing pressure on the industrial supply chain, with delivery times of between three and four years for very high voltage transformers and backup generators, a problem that is exacerbated by the global shortage of copper.

Spain: renewable leadership and economic opportunity

Despite these obstacles, the document places Spain, and especially Aragón alongside emerging markets such as Madrid and Milan, among the regions best positioned to absorb the growth that is shifting away from the major traditional European hubs (Frankfurt, London, Amsterdam, Paris, and Dublin), which are already practically saturated in terms of land and energy availability.

This advantage is supported by its good international connectivity, the abundance of land, and leadership in renewable energy. In 2025, Spain covered 55.5% of its electricity generation with clean sources (56.6% if self-consumption is included) and added almost 10 GW of new wind and solar capacity.

If regulatory and grid bottlenecks can be resolved, the deployment of data centers in Spain could mobilize those 66.900 billion euros by 2030, including equipment, software, integration, and associated services, of which about 25.000 billion euros would correspond to works and preparation of the facilities.

Energy consumption, employment, and digital sovereignty

Regarding the impact on electricity demand, the International Energy Agency (IEA) expects that the global consumption of data centers will rise from 415 terawatt-hours (TWh) in 2024 to 945 TWh in 2030. In Europe, the increase would be from 96 TWh to 168 TWh, reaching already 19% of total electricity consumption in Ireland.

Against this challenge, the report highlights the role of the circular economy—“reusing half of Europe’s residual heat would heat four million households”—and cooling solutions that do not depend on freshwater in regions with water stress.

In the employment arena, the European Association of Data Centres (EUDCA) estimates that direct, indirect and induced employment linked to the sector in Europe will rise from 369,000 full-time equivalent positions in 2024 to about 778,000 in 2031. However, it warns of the urgency of training qualified professionals in electricity, refrigeration and cybersecurity to prevent talent shortages from stalling growth.

The 'White Paper' also examines the issue of digital sovereignty in a European market where local providers retain only 15% of the business 'cloud'—cloud computing services—(compared with 29% in 2017), while close to 70% is in the hands of major U.S. companies such as AWS, Microsoft and Google.

To reduce this dependence, the report proposes implementing single windows inspired by models such as the Planes de Interés General de Aragón (PIGA) and ensuring that public contracts are interoperable, so that Administrations are not tied to a single provider.

European response to the United States and practical solutions

With the aim of competing with the United States—whose hyperscalers plan investments of 735,000 million dollars in 2026 and which in 2024 developed 40 major foundational AI models compared with only three in Europe—Brussels is pushing the plan "InvestAI" (200,000 million and seven gigafactories), 19 AI factories, 10,000 'edge' nodes (centers close to the user to reduce latency) and the future law "CADA".

This regulation provides for the creation of Acceleration Zones and aims to triple European capacity, although analysts consider that, in practice, it will only manage to double it.

Among the specific measures included in the report are the Portuguese system of auctions and financial guarantees to prevent speculation in electrical capacity, the rollout of regional 5 MW centers aimed at local services, the use of AI itself to free up to 175 GW in existing grids, and training programs such as "Think Big Space" and "AWS re/Start" in Aragón, which have already reached more than 7,000 schoolchildren and professionals.