The Mestalla faces its last league season as the home of Valencia CF. The stadium, inaugurated in 1923 and one of the venues with the most history in Spanish football, is on the verge of a farewell that the club has been preparing for years while the works on the Nou Mestalla progress to complete the move during the summer of 2027.
The new stadium, located on Avenida de Cortes Valencianas, is set to become the new home of Valencia starting from the 2027-28 season. The club expects the move to take place in the summer of 2027.
A farewell that comes after years of waiting
Valencia began constructing the Nou Mestalla in 2007, but the works were halted for almost 16 years. Construction resumed on January 10, 2025, with a new project and FCC Construcción as the responsible party for the works. The license stipulates that the stadium must be completed within a maximum period of 30 months, that is, by July 2027.
Since then, the project has entered a visible phase of construction. During 2026, pillars, stair towers, and various elements of the roof structure have been installed, while work on the facade and interior spaces is also progressing.
This is how the Nou Mestalla will be
The new stadium will have a capacity for 70,044 spectators and will feature a large roof that will cover the stands. Its structure will be supported by 50 steel pillars and the roof will weigh approximately 4,800 tons. The project also incorporates a photovoltaic installation.
The intention of Valencia is that the venue is not only a football stadium but also a space for leisure and entertainment throughout the year.
The timeline of the move
2007: works on the Nou Mestalla begin.
2009: the works are halted.
January 10, 2025: construction resumes after almost 16 years.
2026: the structure of the roof, the facades, and the interior spaces progress.
July 2027: deadline established by the license to complete the works.
Summer of 2027: the move of Valencia to the Nou Mestalla is scheduled, coinciding with the start of the 2027-28 season.
The last season of Mestalla
With the start of the 2026-27 season, Valencia thus begins what is expected to be its last league season in Mestalla.
The stadium will continue to be the venue for the first team's matches in the coming months before the club completes the planned change of venue for the summer of 2027.
The countdown is already underway: Mestalla faces its farewell while the Nou Mestalla approaches the final stage of construction that has marked the recent history of Valencia CF for almost two decades.