This Thursday, the electricity company Endesa has set in motion the removal of the first of the 19 medium-voltage towers located at the Nevero substation, in Badajoz.
To the area have gone the mayor of Badajoz, Ignacio Gragera; the government subdelegate in Badajoz, María Isabel Cortés; the Director General of Industry, Energy and Mines of the Junta de Extremadura, Raquel Pastor; and the Endesa director for Andalusia, Extremadura, Ceuta and Melilla, Rafael Sánchez Durán, to learn on the ground about the start of the dismantling of the first of the 19 medium-voltage structures that the company is removing in the vicinity of Polígono Industrial El Nevero, after the burial of 6 medium-voltage lines that started from the Nevero substation.
This intervention constitutes the final phase of work that has been carried out since May 2026, coordinated with the Ayuntamiento de Badajoz, and that has allowed 2,500 meters of overhead medium-voltage lines to be buried, to remove nearly 4,000 meters of existing cabling, and, at this moment, to proceed with the removal of the 19 supports through which those overhead lines ran.
The project has also included the adaptation of the outputs of the buried lines from the Nevero substation and represents for Endesa an investment of more than 300,000 euros, as the company details in a press release.
The work, which will continue during the months of November and December, aims to "reinforce the quality of the electricity supply in the area" and allows "advancing in the integration of electrical infrastructure into the urban environment," thus responding to a demand conveyed by residents of the area.
In carrying out the work, a technical team of 20 professionals participates, responsible for dismantling each of the towers, with heights of up to 22 meters and a weight of more than 5,000 kilos, which results in the total dismantling of 47 Tm of metal structure.
The removal of each support is done by means of a large-tonnage crane, which lifts the tower once it has been unanchored from the ground and deposits it in a controlled manner on the ground. Next, the structure is cut and its components are separated for its later recovery, Endesa states, adding that, once the dismantling of all the towers has been completed, in a final phase all concrete footings will be removed, with the result that the works will be completed this month.
All material coming from the towers, as well as the dismantled cable, is being handled by an authorized waste manager, in order to facilitate its recovery and subsequent processing, with the objective of achieving a zero-waste scenario.
These actions are part of the Investment Plan of e-distribución for Badajoz, aimed at the renewal, automation, expansion and improvement of the electricity distribution networks, with the purpose of strengthening supply, raising its quality, and facilitating the progressive integration of renewable energies into those networks.