The Socialist Municipal Group in the Madrid City Council has filed a complaint with the Provincial Prosecutor’s Office so that what they consider an “ination” by the City Hall during the mandatory urban inspections is clarified, after complaints filed in the Junta de Chamartín about the works carried out by the owners of the home in which the PP president, Alberto Núñez Feijóo, currently resides.
The complaint, which Europa Press has obtained, focuses attention on the processing of an urban file opened based on a neighbor’s complaint in 2022 and, according to the information collected in the Socialist written statement, would still have no binding resolution more than four years later.
The document sent to the Prosecutor’s Office specifies that the works, carried out in May 2022 in a property in the district of Chamartín, would have consisted of separating an attic from the home of which it originally formed part.
The affected neighbor attributes these interventions to water leaks in his apartment, located directly below. As stated in the complaint submitted to the Public Ministry, he reported the facts to the City Hall in 2022, reiterated his complaints in 2025, and sent writings and reports from an architect without, as he argues, having received any response.
From Socialist ranks, they consider it essential to clarify whether this delay is due to “administrative negligence” or if some kind of “favoritism” could have occurred, as they have pointed out in a statement. The mayor of Madrid, José Luis Martínez-Almeida, rejected this Monday having given any instruction regarding the processing of the file, said he was unaware of the neighbor’s complaint, and defended that the work was carried out by the property before Feijóo arrived in the capital, emphasizing that the PP leader is neither and has never been the holder of the property.
REQUESTS THE ENTIRE MUNICIPAL FILE
In the written statement, signed by the Socialist councilor Antonio Giraldo and addressed to the Section of Environment and Urban Planning, it is requested that, as applicable, investigative proceedings be opened to obtain the complete municipal file and the related files, as well as the writings and reports provided since 2022 and all municipal actions that appear.
The councilor explains that on October 7 of last year he requested a copy of the planning file, which was delivered to him on the 22nd of the same month and included requests for a report to the Environmental and Urban Scene Service, but did not incorporate documentation subsequent to those requests that would substantiate inspections, technical or legal reports, requirements, or a decision regarding a possible planning offense.
In addition, on November 17, he filed a new request for information to find out what actions had been carried out since the initiation of the file, the reports that had been issued, the reasons why it was still not being resolved, and the expected date for its conclusion, without, as of November 24, having received a reply, according to what is stated in the complaint.
The document also mentions journalistic information pointing to the fact that a municipal technician may have drawn up an inspection record on November 5 of last year. However, the council member clarifies that the copy of the file in his possession is prior to that date, that he does not have such a record, and that he does not know whether the visit was actually carried out, whether there were prior inspections, what was checked, and what measures were taken afterwards.
For that reason, he asks the Public Prosecutor’s Office that it obtain the record, if it exists, and verify whether inspections prior to that were ordered, attempted, or carried out, as well as what work was carried out, at what moment, and whether they had the necessary planning permits.
He also demands that the municipal authorities responsible for driving the processing of the file and ordering the inspection be identified, when they became aware of the written submissions and reports, what decisions they made, and what reasons are recorded for the delay.
With regard to possible criminal liability, the complaint refers to Article 320(1) of the Criminal Code, which punishes the deliberate omission of mandatory urban inspections by an authority or public official.
Along these lines, the document asks that it be determined whether there was a specific duty to inspect before the possible visit on November 5, who was obliged to do so, and whether he failed to comply with it knowingly.
MAROTO DEMANDS "LIGHT AND A FULL TRANSCRIPT"
The Socialist spokesperson on the City Council, Reyes Maroto, has said that her group has gone to the Prosecutor's Office because it wants "light and records" to clarify "how far the responsibility of the mayor of Madrid goes" and whether planning regulations apply equally to all residents of Madrid, "regardless of his or her surname or of his or her party card".
"The same equation that we already saw in the apartment where Mrs. Ayuso lived is being repeated. Neighborhood complaints, alleged urban planning irregularities, and a mayor who downplays the facts. And it is that in this equation there is a common denominator, Mr. Almeida," she said.
The Socialist leader also demanded explanations from the president of the 'populares' about the conditions of the rental of the home where he resides. "Who pays the rent? Is there any kind of compensation?", she asked.
"We ask for transparency from both Mr. Almeida regarding urban planning legality and also from Mr. Feijóo regarding the conditions of this rental," she added.
ALMEIDA DEFENDS THAT IT CORRESPONDS TO TECHNICIANS
Almeida said this Monday that he has not given instructions about any of the nearly 9,000 urban discipline proceedings that are opened each year in the city, including the one relating to the property where Feijóo lives.
The mayor said that in the Chamartín Municipal Board "there are more than twenty proceedings in the same situation." "It is normal for them to be processed more slowly because they are proceedings that have their own complexity; they are not straightforward, and it is the technical services that correspond to determine the priority they may have, not the mayor," he argued.