The Central Operational Unit (UCO) of the Guardia Civil has informed the National Court that it has detected possible criminal irregularities in the duplication works of the tunnels of Belate, awarded in December 2023 by the Government of Navarre, which is chaired by the socialist María Chivite.
The investigators have located official documentation from different bodies of the Foral Community, mainly from the Cámara de Comptos, which points to possible offenses both in the contracting procedure and in the subsequent execution of the contract.
On Wednesday, the judge of the National Court Ismael Moreno ordered that the new police document, dated November 24, be added to the separate file of the Koldo case in which he investigates alleged irregularities in the awarding of public works contracts. He has also forwarded the document to the Prosecutor’s Office and to the parties that have appeared.
The Government of Navarre awarded the works on December 26, 2023 for 62.88 million euros, excluding VAT, to a Temporary Business Union (UTE) made up of Acciona Construcción, Excavaciones Fermín Osés and Servinabar 2000, a company in which, according to the investigations of the Guardia Civil, the former PSOE Organization secretary Santos Cerdán held a 45% stake.
Irregularities in the award
The UCO gathers the objections raised by three members of the tender board regarding the justification of the technical scores that ultimately determined the award of the works.
The investigators also point out that the president of the tender board knew the assessments of the other members before issuing his own and that the technical documentation of the bids was stored in a network unit to which employees of the Directorate General of Public Works and Infrastructures could access.
The award had already been the subject of a report by the Office of Good Practices and Anti-Corruption of Navarre, which in September 2025 considered that the contract was null and void as a matter of law. The Foral Executive then disagreed with the conclusions of the body.
A cost overruns of more than seven million euros
The new Guardia Civil report also analyzes the modification of the contract and the warnings of the auditor of the Cámara de Comptos Miguel Ángel Aurrecoechea, who stated before the Parliament of Navarre that he had noticed possible indications of a crime in its execution.
The auditor questioned that the foral Administration had to assume at least €7.54 million in additional costs, considering that part of the expenses included in the contract modification did not fit within the assumptions provided for in the Foral Law on Public Contracts.
The modification was approved on 28 May 2025 by the Directorate General of Public Works and Infrastructures and was rendered void on 17 September 2026.
The UCO considers that the auditor’s statement could help clarify the facts, although the judge has not yet ordered his summons.
Chivite has defended the legality of the award
The President of Navarra has defended the actions of her Government on different occasions. In June 2025, before the foral Parliament, she stated that the works’ award procedure had been "completely legal and transparent" and reminded that neither she nor the ministers of Territorial Cohesion formed part of the contracting bodies.
The National Court has formally added the Belate tunnels contract to the investigation on 27 July. The latest ruling by Ismael Moreno is limited to incorporating the new official request from the Guardia Civil into the case and does not order new imputations.