Mestalla begins its farewell: dates, works, and how the move to Valencia's new stadium will be.

Valencia faces the last season planned in its historic stadium while the Nou Mestalla progresses with the aim of opening its doors in the summer of 2027.

Add DEMÓCRATA to Google

Ask FREN

Published

2 minutes

Most read

Elecciones 29N · Encuestas

La media de las encuestas

Media a 23 de noviembre de 2026 · 22 institutos

  • PP31,3 %
  • PSOE28,6 %
  • Vox18,3 %
  • Frente Amplio6,2 %
  • ERC2,6 %
01020304050ene 2024jul 2024ene 2025jul 2025ene 2026jul 2026

Media del último estudio de cada instituto en 30 días y su evolución semanal desde el 23J. Partidos con al menos un 2 %.

Todas las encuestas

Elecciones generales del 29 de noviembre · Demócrata

The Mestalla faces its last league season as the home of Valencia CF. The stadium, inaugurated in 1923 and one of the venues with the most history in Spanish football, is on the verge of a farewell that the club has been preparing for years while the works on the Nou Mestalla progress to complete the move during the summer of 2027.

The new stadium, located on Avenida de Cortes Valencianas, is set to become the new home of Valencia starting from the 2027-28 season. The club expects the move to take place in the summer of 2027.

A farewell that comes after years of waiting

Valencia began constructing the Nou Mestalla in 2007, but the works were halted for almost 16 years. Construction resumed on January 10, 2025, with a new project and FCC Construcción as the responsible party for the works. The license stipulates that the stadium must be completed within a maximum period of 30 months, that is, by July 2027.

Since then, the project has entered a visible phase of construction. During 2026, pillars, stair towers, and various elements of the roof structure have been installed, while work on the facade and interior spaces is also progressing.

This is how the Nou Mestalla will be

The new stadium will have a capacity for 70,044 spectators and will feature a large roof that will cover the stands. Its structure will be supported by 50 steel pillars and the roof will weigh approximately 4,800 tons. The project also incorporates a photovoltaic installation.

The intention of Valencia is that the venue is not only a football stadium but also a space for leisure and entertainment throughout the year.

The timeline of the move

2007: works on the Nou Mestalla begin.
2009: the works are halted.
January 10, 2025: construction resumes after almost 16 years.
2026: the structure of the roof, the facades, and the interior spaces progress.
July 2027: deadline established by the license to complete the works.
Summer of 2027: the move of Valencia to the Nou Mestalla is scheduled, coinciding with the start of the 2027-28 season.

The last season of Mestalla

With the start of the 2026-27 season, Valencia thus begins what is expected to be its last league season in Mestalla.

The stadium will continue to be the venue for the first team's matches in the coming months before the club completes the planned change of venue for the summer of 2027.

The countdown is already underway: Mestalla faces its farewell while the Nou Mestalla approaches the final stage of construction that has marked the recent history of Valencia CF for almost two decades.

More key points, information and questions with FREN

AI-GENERATED CONTENT

What are the pending administrative procedures for the completion of Nou Mestalla before its opening in 2027?

Based on the official documentation from the City Council of València and the Generalitat consulted, there is no closed list of “pending procedures” for Nou Mestalla, but there is a set of conditions and administrative steps that must be fulfilled for the stadium to be completed and open with guarantees by 2027. These steps are mainly concentrated in the municipal urban planning and financial areas, and in the future licenses and technical controls prior to opening to the public.

In summary, before opening it will be necessary to: complete the urban planning procedures related to the stadium, complete the external audit and the deposit of economic guarantees, fulfill obligations with the Benicalap sports center, and obtain construction, activity, and opening licenses with all favorable sectoral reports (security, mobility, urban services, etc.).

1. Municipal urban planning and economic conditions

The bulk of the currently known requirements are set in the “urban planning sheets” and agreements approved by the City Council of València in 2024–2025:

  • Binding conditions for the new stadium: the Plenary approved in July 2024 the modification of the Valencia CF ATE and the urban planning sheets that set the conditions for Nou Mestalla (areas “old Mestalla” and “Corts Valencianes”). Without executing and completing the stadium, the club cannot benefit from the urban planning capital gains associated with its lands (Plenary note 07/23/2024).
  • External audit and bond: the City Council has launched an independent audit to determine the real cost of finishing the stadium. The result will serve to set the bond that Valencia CF must deposit as a guarantee that it will complete the work; without this bond, the urban rights cannot be materialized (audit, 10/23/2024).
  • Penalty regime and loss of capital gains: if the club fails to meet the deadlines of the construction license (delay in starting, stoppage, or non-completion on time), the special planning would become void and the urban capital gains would be completely eliminated, reverting to the previous zoning (Urban Planning Commission, 07/17/2024).
  • Payment for the Benicalap sports center: both the urban planning motion of July 2024 and the plenary agreement of October 2025 condition the obtaining of licenses on lucrative lands and the compatibility of tertiary uses around the stadium on the prior payment of 11.2 million euros to finance the municipal sports center of Benicalap (urban planning 07/17/2024 and Plenary 10/28/2025).
  • Detailed study of the surroundings: in April 2025 the Governing Board initiated the consultation and public information process of the detailed study of the Nou Mestalla surroundings. Until this procedure is completed (sectoral reports, allegations, final approval), the detailed planning of the area will not be fully closed (Governing Board 04/25/2025).
  • Work monitoring: the Plenary agreed in March 2025 to require the club to provide monthly certifications of the Nou Mestalla construction to verify compliance with the committed deadlines (Plan + Housing, 03/25/2025).

2. Licenses and authorizations before opening

Municipal and regional documents do not yet detail a specific opening license for 2027, but allow inferring the major blocks of pending procedures typical of an infrastructure of this type:

  • Construction and building license: the City Council has indicated that the club “will not have a license” while it does not fulfill the economic obligations (Benicalap case). To reach the opening in 2027 it is essential to:
    • Have the license for completion of the stadium construction.
    • Execute the works according to the approved project and license conditions.
    • Demonstrate through the audit that the budget is sufficient and executable.
  • Activity, first occupancy, and opening licenses: as seen in other stadiums (e.g., the Spotify Camp Nou case in Barcelona, cited in the press), the council only grants the first occupancy and activity license when:
    • All safety deficiencies have been corrected (evacuation, fire protection, structures, accessibility, etc.).
    • There are favorable reports from municipal services (activity licenses, mobility, water cycle, supplies, etc.) and, if applicable, from Civil Protection and other regional bodies.
    Nothing in the sources indicates that these reports have already been issued for Nou Mestalla; they are part of the final steps before opening to the public.
  • Integration with regional regulations: the Generalitat has approved rules to streamline procedures and reduce overregulation (for example, Law 3/2026 on urgent measures against overregulation and procedure streamlining, DOGV 07/02/2026). Although it does not specifically mention Nou Mestalla, it conditions:
    • The processing of urban and environmental licenses for large projects.
    • The coordination between Consell and municipalities in projects declared of regional interest.
    In practice, the stadium must comply with this framework regarding licenses, reports, and, if applicable, environmental evaluations related to its surroundings.

3. What can be considered “pending” looking towards 2027

With the available information, the pending administrative procedures for Nou Mestalla to open in 2027 can be summarized as:

  • Complete the municipal urban planning procedures (detailed study, management sheets, possible complementary agreements).
  • Complete and apply the external audit, deposit the bond, and, if applicable, update guarantees as the work progresses.
  • Deposit the 11.2 million euros for the Benicalap sports center, a prior condition for certain licenses and tertiary uses associated with the stadium.
  • Obtain and comply with the construction completion license, without incurring breaches that would annul the urban capital gains.
  • Pass the phase of activity, first occupancy, and opening licenses, with all favorable sectoral and safety reports, both municipal and regional.

The 2027 horizon is, therefore, a political and planning objective that will only be legally consolidated if these requirements are completed in time and form.

What powers does a football club like Valencia CF have regarding the management and operation of sports infrastructures according to Spanish legislation?

A professional club like Valencia CF, which legally operates as a sports public limited company (SAD), does not have its own “public powers” over infrastructures, but rather a set of private management faculties over its assets and, if applicable, rights derived from concessions or contracts with the Administrations owning the stadiums or facilities. All this is framed within a state and local regulatory framework that sets important limits in patrimonial, urban planning, security, accessibility, and public event matters.

(1) When the club is the private owner of the facility

If the stadium or sports city is owned by the club/SAD itself, it acts like any private property owner:

  • It can possess, maintain, renovate, and economically exploit the facility (ticket sales, hospitality, space rental, advertising exploitation, compatible tertiary uses, etc.), as long as it respects general regulations (urban planning, security, accessibility, noise, environment, etc.).
  • As a SAD, its basic framework is in Royal Decree 1251/1999, of July 16, on sports public limited companies (BOE): it sets the corporate regime, minimum capital, economic information to the Higher Sports Council, etc., but does not grant public powers over the stadium, rather it reinforces the transparency and solvency of the managing entity.
  • Law 39/2022, on Sport (BOE) recognizes the importance of facilities for the sports system and requires them to meet standards of accessibility, security, and sustainability, but ownership and operation are basically governed by civil, commercial, and urban planning law.
(2) When the club is a concessionaire or user of public facilities

It is very common that the stadium or sports city is of municipal or regional ownership and is granted to the club through a concession or usage contract. In that case:

  • Law 33/2003, on Public Administrations’ Assets (BOE) applies, and for local entities, the Regulation of Local Entities’ Assets, approved by Royal Decree 1372/1986 (BOE). These rules distinguish:
    • Common use of public domain (general citizen access).
    • Privative or abnormal use (exclusive occupation or intended for a specific service), which requires an administrative concession.
  • The municipal stadium or sports complex is usually considered a public domain asset assigned to a service. For the club to exploit it exclusively (matches, commercial exploitation, events), there must be a public domain concession or other enabling title, usually awarded by tender and with a maximum term (up to 99 years unless special rule), fee, investment and maintenance obligations, etc., according to the articles on privative use and concessions of the Regulation of Local Entities’ Assets.
  • Within that concession, the club has ordinary management powers of the facility (operation, maintenance, permitted sub-exploitations), but cannot alter the public purpose of the asset nor substantially modify works or uses without authorization from the owning Administration and without complying with urban planning regulations.
(3) Limits of urban planning, security, accessibility, and public events

Whether the club is owner or concessionaire, its actions on the stadium or sports city are subject to a set of transversal rules:

  • Urban planning and licenses: municipal urban planning and, if applicable, sectoral (e.g., coasts, historical heritage) set the permitted uses, building rights, heights, parking, etc. Any relevant work or change of use requires urban licenses and sometimes environmental assessments.
  • Security and public events: the classic framework is the General Regulation of Police of Public Events and Recreational Activities, approved by Royal Decree 2816/1982 (BOE), partially displaced by regional regulations and by Law 19/2007, against violence, racism, xenophobia, and intolerance in sport (BOE) and its Regulation, Royal Decree 203/2010 (BOE).
    • They impose on the club, as event organizer, obligations of access control, capacity, video surveillance, seat numbering for all spectators, individual risk plans, security protocols, and internal regulations of the venue.
    • They foresee responsibilities and sanctions for non-compliance (both for the club and fans).
  • Accessibility and Building Technical Code: structural safety, fire safety, evacuation, etc. are governed by the Building Technical Code (Royal Decree 314/2006 and its amendments), including Royal Decree 173/2010 on accessibility and recent regulations such as Royal Decree 193/2023 on basic accessibility conditions for publicly used goods and services. Law 39/2022, on Sport reinforces this approach by requiring sports facilities to meet at least standards of universal accessibility, safety, and sustainability.

In summary, a club like Valencia CF can manage and operate its stadiums and sports cities with broad private faculties (build, renovate, commercially exploit) and, if applicable, as concessionaire of public facilities, but always framed within a regime of public domain and urban planning that sets the use framework and a dense network of security, accessibility, and anti-violence in sport regulations, which intensely condition how these infrastructures are designed, maintained, and operated.

What have been the results of Valencia CF in the latest club presidential elections and how is its board of directors currently composed?

In the consulted documentation, there is no reference to any recent elections for the presidency of Valencia CF with member voting, nor is there a detailed list of the current composition of the board of directors. What is recorded is that, in March 2025, the board appointed Kiat Lim as the new club president replacing Layhoon Chan, within the framework of the Lim family ownership.

Results of the latest “elections” for the presidency of Valencia CF

The sources consulted only provide information about the change in presidency, not about an electoral process open to members with candidacies, campaigns, and vote counting as occurs in other clubs (for example, in FC Barcelona elections, which are described in detail in the press). In the case of Valencia CF, what is documented is an internal appointment made by the governing body of the sports public limited company.

Specifically, the newspaper ABC reports that, on March 4, 2025, the club announced by statement that:

  • “The Board of Directors of Valencia CF is pleased to announce the appointment of Kiat Lim as the new club president, a position he will officially assume on March 5, 2025” (ABC news).
  • It is indicated that Kiat Lim had been a director of Valencia CF since 2022 and that he is the son of the main shareholder, Peter Lim.
  • It is emphasized that the change is justified as a reaffirmation of the Lim family’s “long-term commitment” to the club.
  • The then president, Layhoon Chan, states that “I am pleased to pass the baton to Kiat Lim” and thanks the support received during her term.

Nowhere in that information, nor in the rest of the reviewed documents, is there mention of a member vote nor are there data on participation, counting, or vote distribution among candidacies. What is described is a board of directors agreement in an entity that operates as a sports public limited company, where the presidency is decided by the corporate body representing the shareholders.

Therefore, it is not possible to provide “electoral results” in the strict sense (census, percentage of votes, difference between candidates) because the sources only document a corporate appointment of the new president, without an electoral process open to the social mass comparable to other member-owned clubs.

Current composition of the board of directors of Valencia CF

Searches have scoured general press, documentary databases, and institutional notes with broad term combinations such as “Valencia CF board of directors,” “board members,” “list of directors,” or “Valencia CF governance structure” in the recent period (2019–2026).

However, no document has been found that explicitly and completely offers the nominative and updated list of members of the Valencia CF board of directors (directors, positions, possible independents, etc.).

The only clear detail derived from the sources is:

  • The main shareholder is the Lim family, through Peter Lim.
  • In 2025, the board itself appointed Kiat Lim as club president, replacing Layhoon Chan, confirming that the shareholder family retains control of the governing body (same ABC news).

Beyond these data, the news focused on Valencia CF found in the research refer to the club’s relations with public institutions —for example, regarding the urban planning of Nou Mestalla and the conditions set by the City Council of València in the urban planning sheets— but do not include the organic detail of the board of directors (number of directors, identity of all of them, and specific positions).

Conclusion and how to access more precise information

With the information available in the consulted sources, it can only be stated with certainty that:

  • The last renewal of the presidency took place in March 2025, when the board appointed Kiat Lim president of Valencia CF, replacing Layhoon Chan, with no member elections with public results recorded.
  • There is no complete and verified list of the current members of the board of directors in this database.

To obtain the fine details (names of all directors, status of each, appointment dates) and confirm if there has been any internal electoral call in the not recent past, one would have to go directly to:

  • The official communications of Valencia CF on its corporate website.
  • The Commercial Registry, where the administration positions of public limited companies are registered.
  • Corporate reports or issuer brochures, if the club or its corporate vehicles have published recent financial documentation.

In the absence of those specific documents, any attempt to list names or concrete “electoral results” would go beyond what the sources allow to support.

Play

Test your knowledge with FREN!

How much do you know about this topic? Answer the following 3 questions.

When is Valencia CF expected to complete its move to the Nou Mestalla?

Question 1 of 3

What will be the approximate capacity of the Nou Mestalla?

Question 2 of 3

How many years were the works on the Nou Mestalla halted before resuming in 2025?

Question 3 of 3